November 25, 2026
Officials at the commissioning of the new Billiri transmission substation in Gombe State on 19 November 2026

Officials at the commissioning of the new Billiri transmission substation in Gombe State on 19 November 2026. Photograph: Voice of Nigeria.

Nigeria’s Federal Government has commissioned a new 120-megavolt-ampere (MVA) transmission substation in Billiri and upgraded the Gombe Transmission Substation, doubling the latter’s upstream transformation capacity to 600MVA in a development expected to improve electricity supply across parts of the North-East.

Minister of Power Joseph Olasunkanmi Tegbe commissioned the facilities in Gombe State on Thursday, 19 November 2026. The work includes a new Billiri substation fitted with two 60MVA transformers, an additional 300MVA transformer at the Gombe facility and the replacement of an older 30MVA transformer with a 100MVA unit.

New Billiri facility

The Billiri 132/33kV substation has a combined transformation capacity of 120MVA, equivalent to about 96 megawatts. It is equipped with six outgoing 33kV feeders and is expected to strengthen bulk electricity supply to Billiri, Numan in neighbouring Adamawa State and adjoining communities.

The project addresses longstanding transmission constraints affecting households, businesses and public services in the area. The commissioning report carried by Voice of Nigeria said the facilities were funded by the World Bank. The new Billiri installation is intended to provide another point through which bulk electricity can be supplied to communities within the Jos Electricity Distribution Company franchise area.

At the Gombe Transmission Substation, the installation of an additional 300MVA, 330/132kV transformer has doubled upstream transformation capacity from 300MVA to 600MVA. At the lower voltage level, replacing an existing 30MVA, 132/33kV transformer with a 100MVA unit has raised downstream transformation capacity from 150MVA to 220MVA, equivalent to about 176MW.

The two figures describe different parts of the transmission system. The 600MVA rating is the Gombe station’s upstream capacity at the 330kV level, while 220MVA is its downstream capacity at the 132/33kV level. They should not be added together as though they represent new electricity generation.

More capacity for the North-East

Tegbe said the Gombe upgrade was expected to improve electricity supply to more than 70,000 additional households in Gombe and neighbouring parts of the North-East, including Yobe State. The estimate describes the potential reach of the expanded infrastructure. It does not mean that 70,000 new household connections have already been completed.

The Minister said the facilities were designed to address infrastructure constraints that had limited the productive capacity of communities around Billiri and Gombe. He urged residents to protect the installations from vandalism, saying they had been built for local use: “They’ve been built for you and for your use.”

Transmission Company of Nigeria Managing Director and Chief Executive Officer Sule Ahmed Abdulaziz said electricity demand in Gombe and the areas served by the station had outgrown the previous configuration. He said the upgraded equipment would give system operators greater flexibility to move electricity through the network and increase the amount that Jos Electricity Distribution Company could receive for consumers. “The new transformers provide our system operators with greater operational flexibility,” he said.

Abdulaziz also urged Jos DisCo to increase its offtake of available power so that the additional transmission capacity could translate into better service for customers. The call highlights a practical condition for the project’s success: additional capacity at a transmission station must be matched by sufficient electricity generation and a distribution network capable of delivering that power to homes and businesses.

A multi-year project

The Gombe reinforcement was not conceived and delivered within a single administration. Abdulaziz said TCN awarded the contract in June 2021 and completed the project in June 2026. The commissioning took place under President Bola Tinubu’s administration, but the contract award predates his inauguration in May 2023. An accurate account therefore recognises the multi-year planning and work by TCN, its technical teams and contractors, alongside the administration that oversaw completion and formally commissioned the facilities.

The Gombe State Government was represented at the ceremony by its Commissioner for Energy and Mineral Resources, Sanusi Ahmed Pindiga, on behalf of Governor Muhammadu Inuwa Yahaya. Pindiga commended cooperation between the state and federal authorities and referred to the Electricity Act 2023, which provides the wider legal framework for electricity-sector participation and reform. The Act is part of the policy environment, while the substations and transformer installations are specific infrastructure projects delivered through TCN and its partners.

The projects are intended to support commercial activity, agriculture, small businesses and public services in communities that have faced limits in the amount of electricity the network could carry. Their operational value will depend on maintenance, protection from vandalism, adequate generation and the ability of distribution operators to take and deliver the available power.

For residents and businesses in Gombe, Billiri and neighbouring communities, the measure of success will be whether the new capacity produces a more dependable electricity supply. The commissioning marks a significant expansion of the North-East transmission network, while the next stage rests on effective operation of the facilities and the distribution of electricity to consumers.